382 days
904.2 hours
13 partipants

the building of N622JC

a Zenith CH 750 CruZer

Milestone: Avionics

Avionics installed and functional.

See Wiring Plan for more information on avionics and other items requiring wiring.


Work Log Entries

Date Title Activity Time
June 8, 2021 Avionics - VOR Antenna Mount Building 6.0
May 5, 2021 Wings - Magnetometer Building 3.0
February 2, 2021 Avionics - Wiring Under Seat Building 4.5
February 1, 2021 Avionics - Transponder Coax Building 3.0
January 30, 2021 Avionics - Antenna Mounting Building 4.5
January 29, 2021 Avionics - Wiring Building 3.5
January 27, 2021 Avionics - CAN BUS Wiring and Com Antenna Doubler Building 3.0
January 25, 2021 Avionics - Nav Power and Static Ports Building 6.0
January 24, 2021 Avionics - Power Applied Building 3.0
January 23, 2021 Avionics - Flight Switches and Reinforce Center Rack Building 7.0
January 22, 2021 Avionics - Work Towards Power Building 2.5
January 21, 2021 Avionics - Audio (GMA 245R) LRU Mounting Building 3.5
January 20, 2021 Avionics - GAD 27 and GEA 24 Mounting Building 3.0
January 19, 2021 Avionics - Radio Rack and LRU Mount Building 6.0
January 18, 2021 Avionics - Mount Panel Units Building 8.5
January 16, 2021 Avionics - Panel Rack Building 5.5
January 14, 2021 Avionics - Center Console Building 1.5
January 11, 2021 Avionics - Populate Center Console Building 4.5
January 9, 2021 Avionics - Center Console Building 2.0
January 8, 2021 Avionics - Wiring Plan Planning 3.0
January 7, 2021 Avionics - Center Console and Mock Switch Panel Building 2.8
January 6, 2021 Avionics - Center Console Mock Building 3.0
December 14, 2020 Avionics - Organize Avionics Boxes Preparing 4.0
October 9, 2020 Build a Mock Panel Building 9.0
October 3, 2020 Powering on the G3X Building 2.5