209 days
447.9 hours
13 partipants

the building of N622JC

a Zenith CH 750 CruZer

Milestone: Fuselage

Describe the milestone here.


Work Log Entries

Date Title Activity Time
February 5, 2021 Avionics/Fuselage - More Wiring and Nose Strut Building 3.0
January 2, 2021 Fuselage - Co-pilot Seat and Rudder Pedals Building 7.0
January 1, 2021 Fuselage - Pilot Seat - 2 Building 3.0
December 31, 2020 Fuselage - Pilot Seat Building 6.0
December 30, 2020 Fuselage - Control Stick Building 6.5
December 29, 2020 Fuselage - Panel Final Drilling Building 2.5
December 26, 2020 Fuselage - Controls Building 3.0
December 24, 2020 Fuselage - Cabin Curved Doublers - Install Building 2.0
December 23, 2020 Fuselage - Cabin Curved Doublers Building 3.5
December 21, 2020 Fuselage - Rivet Aft Fuselage and Cabin Building 4.0
December 20, 2020 Fuselage - Fix Cabin Frame Longerons Building 2.0
December 19, 2020 Fuselage - Finish Main Gear Mounts Building 4.5
December 18, 2020 Fuselage - Finish 4 Point Harness Building 2.5
December 16, 2020 Fuselage - Point Harness Prep Building 3.0
December 15, 2020 Fuselage - Prep for Cabin Frame Install Building 3.5
December 13, 2020 Fuselage - Prime and Paint Building 16.0
December 9, 2020 Fuselage - Prep steel for primer and paint Building 2.5
December 8, 2020 Fuselage - Gear Channel and Rudder Pedals Building 5.0
December 7, 2020 Fuselage - Seats and Gear Channel Building 4.5
December 5, 2020 Fuselage - Cabin Frame Building 8.5
December 4, 2020 Fuselage - Baggage Session 2 Building 1.0
December 3, 2020 Fuselage - More Join and Baggage Work Building 4.0
December 1, 2020 Fuselage - Join aft and forward fuselage Building 4.0
November 29, 2020 Fuselage - Baggage Session 1 Building 6.0
November 28, 2020 Fuselage - Aft Join Building 3.5
November 28, 2020 Fuselage - Forward Session 4 Building 2.5
November 27, 2020 Fuselage - Forward Session 3 Building 7.5
November 26, 2020 Fuselage - Forward Session 2 Building 5.5
November 25, 2020 Fuselage - Forward Session 1 Building 3.0
November 24, 2020 Fuselage - Top Skin Building 2.0
November 24, 2020 Fuselage - Firewall Session 2 Building 1.5
November 23, 2020 Fuselage - Firewall Session 1 Building 2.5
November 22, 2020 Fuselage - Side Skins Building 8.0
November 21, 2020 Fuselage - Bottom Skin Building 3.5