382 days
904.2 hours
13 partipants

the building of N622JC

a Zenith CH 750 CruZer

Milestone: Tail

Build the horizontal stabilizer and elevator.


Work Log Entries

Date Title Activity Time
May 11, 2021 Tail - Vertical Stabilizer Building 3.5
November 4, 2020 Tail Build Session 12 Building 3.0
October 10, 2020 Tail Build Session 11 Building 3.0
October 6, 2020 Tail Build Session 10 Building 2.2
October 4, 2020 Tail Build Session 9 Building 1.5
October 3, 2020 Tail Build Session 8 Building 2.0
September 27, 2020 Tail Build Session 7 Building 2.0
September 26, 2020 Tail Build Session 6 Building 2.5
September 25, 2020 Tail Build Session 5 - Maybe our first error? Building 1.5
September 24, 2020 Tail Build Session 4 Building 2.1
September 23, 2020 Tail Build Session 3 Building 4.0
September 22, 2020 Watched the Home Built Help Video on applying horizontal stabilizer skin Learning 1.0
September 22, 2020 Tail Build Session 2 Building 2.3
September 22, 2020 Tail Build Session 1 Building 1.7
September 21, 2020 Tail Inventory Preparing 1.0
September 3, 2020 Watched the entire 'How we Built our Zenith CruZer Tail' Learning 3.0