382 days
904.2 hours
13 partipants

the building of N622JC

a Zenith CH 750 CruZer

Fuselage - Rivet Aft Fuselage and Cabin

December 21, 2020 4.0 hours Fuselage Building Jeremy, Samantha

With the gear channel complete and riveted, this has already created a permenant bond between the aft fuselage and cabin frame. We can now rivet a lot more and get some cleco’s back. OK, getting cleco’s back wasn’t our main motivation, we wanted to have another milestone behind us.

After tonight, we now have a fuselage instead of two halves joined with just cleco’s.