Date Title Milestone Activity Time Expense
August 30, 2021 Inspection Day Inspection Building 8.0 0.00
August 29, 2021 Wrap-up Day 35 Fuselage Building 8.0 0.00
August 28, 2021 Wrap-up Day 34 Fuselage Building 4.5 0.00
August 24, 2021 Wrap-up Day 32 Fuselage Building 8.0 0.00
August 23, 2021 Wrap-up Day 31 Fuselage Building 11.0 0.00
August 22, 2021 Wrap-up Day 30 Fuselage Building 9.0 0.00
August 20, 2021 Wrap-up Day 28 Fuselage Building 13.0 0.00
August 19, 2021 Wrap-up Day 27 Fuselage Building 8.0 0.00
August 9, 2021 Wrap-up Day 17 Fuselage Building 3.0 0.00
July 18, 2021 Wrap-up Day 12 Fuselage Building 9.0 0.00
July 16, 2021 Wrap-up Day 10 Fuselage Building 11.0 0.00
July 15, 2021 Wrap-up Day 9 Fuselage Building 10.0 0.00
July 14, 2021 Wrap-up Day 8 Fuselage Building 9.5 0.00
July 12, 2021 Wrap-up Day 6 Fuselage Building 13.5 0.00
July 11, 2021 Wrap-up Day 5 Fuselage Building 9.5 0.00
July 10, 2021 Wrap-up Day 4 Fuselage Building 12.0 0.00
June 2, 2021 Wings - Wings On Wings Building 8.5 0.00
May 29, 2021 Moved to the Hangar Shop Ready Preparing 7.0 0.00
May 1, 2021 Engine - Baffles Engine Building 3.0 0.00
April 22, 2021 Engine - Cowling Engine Building 8.5 0.00
March 10, 2021 Engine - First Start Engine Building 7.5 0.00
February 20, 2021 Engine - Installed Engine Building 9.5 0.00
January 30, 2021 Avionics - Antenna Mounting Avionics Building 4.5 0.00
January 26, 2021 Engine Arrived Engine Building 3.0 0.00
January 23, 2021 Avionics - Flight Switches and Reinforce Center Rack Avionics Building 7.0 0.00
January 9, 2021 Avionics - Center Console Avionics Building 2.0 0.00
January 7, 2021 Avionics - Center Console and Mock Switch Panel Avionics Building 2.8 0.00
December 26, 2020 Fuselage - Controls Fuselage Building 3.0 0.00
December 13, 2020 Fuselage - Prime and Paint Fuselage Building 16.0 0.00
November 28, 2020 Fuselage - Aft Join Fuselage Building 3.5 0.00
November 28, 2020 Fuselage - Forward Session 4 Fuselage Building 2.5 0.00
November 13, 2020 Right Wing - Top Skins Ready for Final Assembly Wings Building 4.8 0.00
November 3, 2020 Inventory Session 1 Kit Purchase Preparing 4.0 0.00
September 27, 2020 Tail Build Session 7 Tail Building 2.0 0.00
September 10, 2020 Chose Registration Number Paperwork Planning 5.0 10.00