382 days
904.2 hours
13 partipants

the building of N622JC

a Zenith CH 750 CruZer

Work Log Entries

Date Title Milestone Activity Time
August 31, 2021 Final Tasks Before Flying Inspection Building 0.0
August 31, 2021 Squawks after Inspection Paperwork Planning 5.0
August 31, 2021 Squawks after Inspection Inspection Building 6.0
August 30, 2021 Inspection Day Inspection Building 8.0
August 30, 2021 Develop Taxi Test Plan First Flight Testing 3.0
August 29, 2021 Wrap-up Day 35 Fuselage Building 8.0
August 28, 2021 Wrap-up Day 34 Fuselage Building 4.5
August 27, 2021 Wrap-up Day 33 Fuselage Building 4.0
August 24, 2021 Wrap-up Day 32 Fuselage Building 8.0
August 23, 2021 Wrap-up Day 31 Fuselage Building 11.0
August 22, 2021 Wrap-up Day 30 Fuselage Building 9.0
August 21, 2021 Wrap-up Day 29 Fuselage Building 13.0
August 20, 2021 Wrap-up Day 28 Fuselage Building 13.0
August 19, 2021 Wrap-up Day 27 Fuselage Building 8.0
August 18, 2021 Wrap-up Day 26 Fuselage Building 5.0
August 17, 2021 Wrap-up Day 25 Fuselage Building 10.0
August 16, 2021 Wrap-up Day 24 Fuselage Building 10.5
August 15, 2021 Wrap-up Day 23 Fuselage Building 2.0
August 14, 2021 Wrap-up Day 22 Fuselage Building 5.0
August 13, 2021 Wrap-up Day 21 Fuselage Building 6.0