382 days
904.2 hours
13 partipants

the building of N622JC

a Zenith CH 750 CruZer

Fuselage - Controls

December 26, 2020 3.0 hours Fuselage Building Jeremy, Jack, Lucas, Angie, Anne

My dad, brother, and sister came over today and we did a little work on the airplane. We got the front control bushing centered, L-angles drilled out on both sides, all deburred and corteced. We stopped short today of riveting.

Today was mostly sharing the project with others, build techniques, etc.