382 days
904.2 hours
13 partipants

the building of N622JC

a Zenith CH 750 CruZer

Wrap-up Day 10

July 16, 2021 11.0 hours Fuselage Building Jeremy, Samantha, Lucas, Al

  • Picked up data plate from engraver
  • Completed pilot side door (lots of window cleaning!)
  • Installed top sunroof (more window cleaning!)
  • Updated all Garmin databases
  • Spent a few hours with Al learning G3X and GNX 375 (very basics)
  • Vertical stablizer fairing fitted and nut plate installation began