382 days
904.2 hours
13 partipants

the building of N622JC

a Zenith CH 750 CruZer

Wrap-up Day 31

August 23, 2021 11.0 hours Fuselage Building Jeremy, Samantha, Lucas

  • Finish riveting the flaperon counter weights – Ran out of AS5 rivets, borrowed some from Curt
  • Make shoulder harness belts the same (one exits up, the other down)
  • Reduce tension on elevator cable bungee
  • Install fender washer, normal washer, cotter pin on flaperon fuse rods
  • Ream all inspection nut plates
  • Tighten ECU static port nut
  • Cotter pin elevator push tube
  • Tighten Avionics switch
  • Ensure fuel lines are not compressed where secured in cabin
  • Touch up chipped paint on flaperon counter weight
  • Remove binding from pitch servo push rod
  • More work on oil door