382 days
904.2 hours
13 partipants

the building of N622JC

a Zenith CH 750 CruZer

Wrap-up Day 34

August 28, 2021 4.5 hours Fuselage Building Jeremy, Samantha, Lucas

  • Installed exhaust pipe
  • Installed two remaining nut plates for Cowling mount
  • Install safety wire in elevator trim hinge
  • Safety wire nose axle bolts
  • Install exhaust pipe springs and safety wire
  • Fit, cut, bent, and drilled rear torque tube support
  • Secured battery charger port in FWF
  • Paint rear torque tube support