382 days
904.2 hours
13 partipants

the building of N622JC

a Zenith CH 750 CruZer

Inspection Day

August 30, 2021 8.0 hours Inspection Building Jeremy, Samantha, Lucas

  • Safety wire right gascolator
  • Reinstall fuel pump relay connectors
  • Fix fuel return line adel clamp (loose around engine mount)
  • Register ELT
  • Hang registration in plane
  • Perform condition inspection
    • Log condition inspection
  • Add gas to each tank
  • Perform ELT self test
  • Calibrate fuel senders (up to 7 gallons)

Inspection Passed!